Ditch 1 20.5 hours | Ditch 2 25.5 hours | Ditch 3 12 hours | Ditch 4 14.5 hours | Ditch 5 27 hours | Ditch 6 16.5 hours | Ditch 7 20 hours | Ditch 8 6.5 hours | Ditch 9 13.5 hours |
|---|
1: Loza3.5 | 1: Walker1 | 1: Johnsson2.5 | 1: Fichtner1 | |||||
2: Gallegos2 | 2: Elton2 | 2: Thornburg3 | ||||||
3: Baune2 | 3: Dickinson2.5 | |||||||
4: Maggard1 | ||||||||
5: Griset1.5 | 5: Brishky2.5 | 5: Gaut2 | 5: Allard1 | |||||
6: Duncan2 | 6: Lueck1.5 | 6: Neumann2 | ||||||
8: Corcoran3 | 8: Molina0.5 | 8: Johns1 | 8: Saunders1 | |||||
9: Powell, M2 | 9: Walker3 | |||||||
10: Rau1 | ||||||||
11: Lopez5 | 11: Siegfried3.5 | |||||||
12: Smith, E4 | 12: Trahan2 | 12: Myers, B1.5 | ||||||
13: Anderson, R1.5 | 13: Russell3 | |||||||
14: Leonard1 | 14: Ortega, A1 | |||||||
15: Carter2 | 15: Hagen4 | 15: Romo1.5 | ||||||
16: Cox2 | ||||||||
17: Callahan2 | 17: Hatton1.5 | |||||||
18: Chandler5 | 18: Reistma2.5 | 18: Kesti3 | 18: Schneider, R2 | |||||
19: Prenovost4 | 19: Azizi2 | |||||||
20: Darrow2.5 | 20: Mandurraga1.5 | 20: Foisy3 | 20: Naehrbass4 | 20: Wood3 | 20: Bandin2 | |||
21: Anzini2 | ||||||||
22: Gonzalez, F1.5 | 22: Thayer1.5 | |||||||
23: Dutton, S2 | 23: Green, Chris3 | 23: Sandidge2 | ||||||
24: Munguia3 | ||||||||
25: Walter1 | 25: Broehm2 | |||||||
26: Kelly, G & M3 | ||||||||
27: Sims2 | 27: McGinnis2 | |||||||
28: Amsden4 | 28: Burkhart1 | |||||||
30: Rose/Funez3 | ||||||||
32: Squires2 | 32: Black2 | |||||||
33: Johnson1 | 33: Shipley3.5 | |||||||